Procedure for commissioning in systems without System Manager


Qualified person

This section describes the procedure of commissioning an inverter that is used in systems without System Manager (e.g. SMA Data Manager).

It provides an overview of the steps, which must be performed in the prescribed sequence.

The system password is also the password for the user interface

The system password assigned via the System Manager is also the password for the user interface of the inverter.

Procedure

See

Commission the inverter.

Commissioning the Inverter)

Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:

  • Direct connection via Ethernet

  • Connection via Ethernet in the local network

Establishing a Direct Connection via Ethernet)

Establishing a Connection via Ethernet in the local network)

Log into the user interface.

Logging into the user interface for the first time)

Select the inverter configuration option. Please note that the SMA Grid Guard code for changing the grid-relevant parameters must be available after completion of the first ten feed-in hours or installation assistant. You can request the SMA Grid Guard code via the Online Service Center.

Layout of the 'Configuring the Inverter' page)

Ensure that the country standard has been configured correctly.

Country standard)

Make further inverter settings as needed.

Changing parameters)

    Also see: