Configuring the active power mode for systems with external setpoint
Qualified person
Requirement:
Installation assistant has been started.
Procedure:
- Select [Save and continue] after each step up until the step Grid management service.
- In the tab Active power mode set the switch Active power setpoint to [On].
- In the drop-down list Operating mode active power setpoint, select the entry External setpoint.
- In the drop-down list Fallback behavior, select the entry Apply fallback values.
- In the Fallback value of maximum active power field, enter the value to which the product should limit its nominal power if communication to the higher-level control unit fails after the timeout time has elapsed.
- In the Timeout field, enter the time that the product should wait until it limits its nominal power to the set fallback value.
- If, in the event of a 0% or 0 W specification, the inverter is not permitted to feed small amounts of active power into the utility grid, select the entry Yes in the drop-down list Grid disconnection for 0% active power setpoint. This ensures that in the event of a 0% or 0 W specification, the inverter disconnects from the utility grid and does not feed in active power.