Commissioning the Inverter


Qualified person

WARNING

Danger to life due to fire or explosion when batteries are fully discharged

A fire may occur due to incorrect charging of fully discharged batteries. This can result in death or serious injury.

  1. Before commissioning the system, verify that the battery is not fully discharged.
  2. Do not commission the system if the battery is fully discharged.
  3. If the battery is fully discharged, contact the battery manufacturer for further proceedings.
  4. Only charge fully discharged batteries as instructed by the battery manufacturer.

Requirements:

  • The AC circuit breaker must be correctly rated and mounted.

  • The product must be correctly mounted.

  • All cables must be correctly connected.

Procedure:

  1. Switch on the AC circuit breaker.
  2. Switch on the battery or the load-break switch of the battery (see documentation of the battery manufacturer).
  3. All 3 LEDs light up briefly. The start-up phase begins.
  4. If th red LED is glowing, an error has occurred that must be rectified Troubleshooting).
  5. Establish a connection to the user interface of the inverter Establishing a connection to the user interface).