Connecting the connections to the automatic transfer switching device

Circuitry overview with Main Panel
Requirement:
The lid of the automatic transfer switching device has been opened or removed.
The installation cover of the automatic transfer switching device has been removed.
Procedure:
- Disconnect the inverter from all voltage sources. See inverter manual.
- Disconnect the AC fuse.
- Connect the PE of the utility grid to the lower connection on the automatic transfer switching device. To do this, unlock the terminal with a flat-blade screwdriver (5.5 mm).
- Connect the PE from the inverter to the upper connection on the automatic transfer switching device. To do this, unlock the terminal with a flat-blade screwdriver (5.5 mm).
- Connect L2 to the utility grid at the GRID L2 terminal on the automatic transfer switching device, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
- Connect L1 to the utility grid at the GRID L1 terminal on the automatic transfer switching device, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
- Connect conductor L2 for the backup loads to the INV L2 terminal on the automatic transfer switching device. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
- Connect conductor L1 for the backup loads to the INV L1 terminal on the automatic transfer switching device. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
- Connect the SPS OUT AC cable to L and N on the automatic transfer switching device, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (3.5 mm).
- Connect the AC cable SPS IN to 1 and 2, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (3.5 mm).
- Connect the conductor N of the utility grid to the terminal block of the automatic transfer switching device.
- Connect the conductor N of the inverter to the terminal block of the automatic transfer switching device.
- Connect the conductor L for the loads to the automatic transfer switching device.
- Ensure that the pre-fuse of the monitoring relay is switched on.