Connecting the connections to the automatic transfer switching device


15705524364

Circuitry overview with Main Panel

Requirement:

  • The lid of the automatic transfer switching device has been opened or removed.

  • The installation cover of the automatic transfer switching device has been removed.

Procedure:

  1. Disconnect the inverter from all voltage sources. See inverter manual.
  2. Disconnect the AC fuse.
  3. 14887435532
  4. Connect the PE of the utility grid to the lower connection on the automatic transfer switching device. To do this, unlock the terminal with a flat-blade screwdriver (5.5 mm).
  5. 15635909516
  6. Connect the PE from the inverter to the upper connection on the automatic transfer switching device. To do this, unlock the terminal with a flat-blade screwdriver (5.5 mm).
  7. 15288307212
  8. Connect L2 to the utility grid at the GRID L2 terminal on the automatic transfer switching device, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
  9. 14887435916
  10. Connect L1 to the utility grid at the GRID L1 terminal on the automatic transfer switching device, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
  11. 15288307596
  12. Connect conductor L2 for the backup loads to the INV L2 terminal on the automatic transfer switching device. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
  13. 14887436300
  14. Connect conductor L1 for the backup loads to the INV L1 terminal on the automatic transfer switching device. To do this, unlock the terminals with a flat-blade screwdriver (5.5 mm).
  15. 14887436684
  16. Connect the SPS OUT AC cable to L and N on the automatic transfer switching device, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (3.5 mm).
  17. 14887553932
  18. Connect the AC cable SPS IN to 1 and 2, as labeled. To do this, unlock the terminals with a flat-blade screwdriver (3.5 mm).
  19. 15635943564
  20. Connect the conductor N of the utility grid to the terminal block of the automatic transfer switching device.
  21. 15635943948
  22. Connect the conductor N of the inverter to the terminal block of the automatic transfer switching device.
  23. 15635982732
  24. Connect the conductor L for the loads to the automatic transfer switching device.
  25. 15907414156
  26. Ensure that the pre-fuse of the monitoring relay is switched on.
  27. Tug lightly to ensure that all conductors are secured in the terminals.