Configuring Feed-In Management
Qualified person
Starting the installation assistant
- Activate the user interface ( > Establishing a connection to the user interface).
- Log in as Installer.
- Start the installation assistant ( > Starting the Installation Assistant).
- Select [Save and continue] after each step up until the step Configure grid management service.
- Make the settings as described in the following.
Setting the connected line conductors
-
In the tab Feed-in management, select the line conductor to which the inverter is connected from the drop-down list Connected line conductors.
Making settings for systems without a higher unit
- Set Feed-in management at the grid-connection point to [On].
- Enter the total PV array power in the field Nominal PV system power.
- In the drop-down list Operating mode of active power limitation at the grid-connection point, select whether active power limitation is to be performed via a fixed specification in percent or in watts.
- In the field Set active power limit at the grid-connection point, enter the value to which the active power at the grid-connection point is to be limited. The value must be set to 0 for zero export.
Making settings for systems with a higher unit
Set Feed-in management at the grid-connection point to [Off].
Activating unbalanced load limitation
Depending on the country data set, unbalanced load limitation may have already been set. In this case, check the settings.
If there are single-phase PV inverters in the system and unbalanced load limitation is requested, set Unbalanced load limitation to [On] and enter the maximum permissible unbalanced load in the field Maximum unbalanced load.
If there are three-phase PV inverters in the system, set Unbalanced load limitation to [Off].
Setting PV inverter feed-in management
- Activate the PV inverter user interface.
- Log in as Installer.
- Start the installation assistant on the PV inverter user interface.
- Select [Save and continue] after each step up until the step Configure grid management service.
- Ensure that the function System control and power limitation is set to [On].
- In the drop-down list Operating mode active power, select the entry Active power limitation P via system control.
- In the drop-down list Operating mode for absent system control, select the entry Use fallback setting.
- In the field Fallback active power P, enter the same value as the one entered for the battery inverter. Where necessary, convert this value into a percentage. This ensures that in systems with Sunny Home Manager, the correct fallback value will be adopted in the event of a communication breakdown between Sunny Home Manager and inverter.
- In the field Timeout, enter the time that the PV inverter is to wait before it limits its nominal power to the set fallback value.
- If, in the event of a 0% or 0 W specification, the PV inverter is not permitted to feed small amounts of active power into the utility grid, select the entry Yes in the drop-down list Grid disconnection at zero export. This ensures that in the event of a 0% or 0 W specification, the inverter disconnects from the utility grid and does not feed in active power.