Cabling plan with BMZ Hyperion, IBC era:powerbase or Axitec AXIstorage LI SH


12133835276

Sunny Tripower Smart Energy with BMZ Hyperion, AXITEC AXIstorage, IBC era:powerbase when using the communication cable provided by the battery manufacturer. If an installation cable is not used, the individual cable ends must be provided with a 12 mm long bootlace ferrule.

Terminal point at inverter

Function

Terminal point at battery

1

CAN H (twisted pair conductors, at least CAT5e)

1

2

Enable

6

3

CAN L (twisted pair conductors, at least CAT5e)

2

4

GND

5

5

Not used

-

6

Shielding (if necessary)

-