Activating Feed-In Operation after Grid Fault


Qualified person

Once the inverter has stopped feed-in operation, you have two options for reactivating feed-in operation:

  • Activate the feed-in operation via the user interface.

  • Activate the feed-in operation via the switch that is connected to the SMA I/O Module.

Activating Feed-In Operation via the User Interface

  • In the parameter group Device > Operation, select the parameter Operating condition and set to MPP.

Activating Feed-In Operation via the Switch that is Connected to the SMA I/O Module

Requirements:

  • The inverter is equipped with one SMA I/O Module.

  • The switch for the manual restart must be connected at the digital input 5 (contact terminal: A3) of the SMA I/O Module.

Procedure:

  • Operate the switch that is connected to the SMA I/O Module.