Activating Feed-In Operation after Grid Fault
Qualified person
Once the inverter has stopped feed-in operation, you have two options for reactivating feed-in operation:
Activate the feed-in operation via the user interface.
Activate the feed-in operation via the switch that is connected to the SMA I/O Module.
Activating Feed-In Operation via the User Interface
In the parameter group Device > Operation, select the parameter Operating condition and set to MPP.
Activating Feed-In Operation via the Switch that is Connected to the SMA I/O Module
Requirements:
The inverter is equipped with one SMA I/O Module.
The switch for the manual restart must be connected at the digital input 5 (contact terminal: A3) of the SMA I/O Module.
Procedure:
Operate the switch that is connected to the SMA I/O Module.