Commissioning Procedure
Qualified person
Before you can commission the inverter, you must check various settings and make changes if necessary. This section describes the procedure and gives an overview of the steps, which must always be performed in the prescribed sequence.
Procedure |
See | |
---|---|---|
|
Connect to the communication interface. |
Installation manual of the communication interface |
|
Check the country data set configuration of the inverter. |
Supplementary sheet with the default settings, type label or display |
|
If the country data set is not set correctly for your country or your purpose, adjust to the required country data set and the corresponding display language within the first ten feed-in hours via the rotary switches in the inverter. | |
|
If the inverter is to communicate with several BLUETOOTH devices, or if BLUETOOTH is not to be used as a type of communication, set the NetID. | |
|
Commission the inverter and start a self-test, if required. |
> Commissioning the Inverter and > Self-Test in Accordance with CEI 0-21 for PV Systems ≤6 kW |