Requirements for Commissioning the System
- The AC circuit breaker must be correctly rated and mounted.
- All products of the system must be correctly mounted.
- Unused enclosure openings must be sealed tightly with filler plugs.
- All cables must be correctly connected.
- The hybrid inverter must be supplied with electric current on the PV side.
- The product settings must correspond to the default settings; the products must not have been commissioned yet.
- The hybrid inverter and the energy meter must be connected to the same network via Ethernet cable.
- The qualified person who is commissioning the system must have a Sunny Portal user account or an SMA ID. In addition, it is recommended for the owner of the system to have access to Sunny Portal.
- In systems with several inverters, the most powerful product should be configured as the System Manager. The battery and the SMA Backup solution must be connected to the System Manager.