Activating SMA Premium via Sunny Portal
Requirements:
- The system must be captured in Sunny Portal powered by ennexOS.
- The System Manager must be configured.
- An energy meter must be installed at the point of interconnection.
- A battery must be installed in the system.
- Depending on normative requirements, the limitation at the point of interconnection must be correctly set.
Procedure:
- Ensure that no Sunny Home Manager 2.0 is configured as a main device in the system.
- Make location settings. Go to [System properties] via [Configuration].
- Enter the details regarding the Location and PV modules.
- In the External access area, check the External parameterization and set Data communication to High if other settings are currently saved.
- In the Automatic updates area, enable the settings of all SMA products.
- Configure the tariff settings via [Configuration] > [Tariffs].
- Go to [Energy management] via [Configuration].
- In the Energy Maximizer area, click the button [Test for free].
- You will be forwarded to the final page.
- Follow the instructions on the interface.
- The free trial period has been activated.
- Go to [Configure] via [Configuration] > [Energy Management] in the Energy Maximizer section. There, check the settings in the Peak load shaving area and adjust if necessary.
- Confirm with [Activate].
- SMA Premium is active and can be viewed under [Configuration] > [Digital Products]. After the trial period (90 days) ends, SMA Premium terminates automatically and does not convert into a subscription service. To continue using SMA Premium, a user with the role of "Owner" must actively purchase a paid SMA Premium subscription during or after the trial period.