Procedure for the Initial Installation and Commissioning of the System
The procedure for installation, electrical connection, and commissioning of the system is described in the following. It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
|---|---|---|
Ensure that the requirements for the installation of the system components are fulfilled. | Manuals of the system components | |
Mount the inverter. | Manual of the inverter | |
Mount backup solution. | Manual of the backup solution | |
Install the SMA Energy Meter or Sunny Home Manager. | Manual of the SMA Energy Meter or Sunny Home Manager | |
Mount the battery. | Manual for the battery | |
Ensure that the requirements for the electrical connection are fulfilled. | Manuals of the system components | |
Connect to utility grid. | Manual of the inverter | |
Connect the inverter to the backup solution. | Manual of the backup solution | |
Connect backup loads to the backup solution. | Manual of the inverter | |
Connect the network cables to the router and other inverters to the inverter. | Manual of the inverter | |
Connect SMA Energy Meter or Sunny Home Manager to the inverter. | Manual of the inverter | |
Connect the data cables of the battery. | Manual of the inverter | |
Connect switch for fast stop to digital input (optional). | Manual of the inverter | |
Connect to the multifunction relay (optional). | Manual of the inverter | |
Connect the PV modules to the inverter. | Manual of the inverter | |
Connect the battery power cables. | Manual of the inverter | |
Connect the additional grounding to the inverter. | Manual of the inverter | |
Commission the system. | Manual of the inverter | |
Make additional settings. | Manual of the inverter | |
Test backup operation. | Manual of the inverter | |