Commissioning Procedure


Qualified person

Procedure

See

Commission each inverter.

Commissioning the Inverter)

Establish a connection to the user interface of an inverter. The following connection options are available to choose from:

  • Direct connection via WLAN

  • Connection via WLAN in the local network

  • Direct connection via Ethernet

  • Connection via Ethernet in the local network

Establishing a connection to the user interface)

Log into the user interface.

Logging In and Out of the User Interface)

Configure the inverter using the installation assistant.

Selecting a configuration option)

Save the configuration of the inverter in a file.

Saving the Configuration in a File)

Establish a connection to the user interface of each additional inverter in the system.

Establishing a connection to the user interface)

Log into the user interface of each additional inverter.

Logging In and Out of the User Interface)

Configure each additional inverter using the configuration file of the first inverter.

Selecting a configuration option)

To monitor the PV system and visualize the PV system data, register in the Sunny Portal and create the system in Sunny Portal or add devices to an existing system.

https://ennexos.sunnyportal.com or https://www.sunnyportal.com