Starting the Installation Assistant
Qualified person
The installation assistant leads you step-by-step through the steps necessary for the initial configuration of the inverter.
Layout of the installation assistant
Layout of the installation assistant (example)
Position | Designation | Description |
---|---|---|
A | Configuration steps | Overview of the installation assistant steps. The number of steps depends on the type of device and the additionally installed modules. The current step is highlighted in blue. |
B | User information | Information about the current configuration step and the setting options of the configuration step. |
C | Configuration field | You can make settings in this field. |
Requirement:
The SMA Grid Guard code must be available to change network-relevant parameters after the first 10 hours of feed-in operation, or after completing the installation assistant. You can request the SMA Grid Guard code via the Online Service Center.
Procedure:
- Open the user interface ( > Establishing a connection to the user interface).
- Log in as Installer.
- Select the menu User Settings ( > Start Page Design of the User Interface) on the start page of the user interface.
- In the context menu, select [Starting the installation assistant].
- The installation assistant will open.