Cabling Plan with Battery-Box Premium HVS/HVM and BCU 2.0

The bridge at the GSI terminal must be inserted during operation.
Upon delivery of the Sunny Boy Smart Energy, there is a jumper wire on the GSI terminal block. This jumper wire must be removed when a switch for the fast stop is connected. Once the jumper wire has been removed and no switch is connected, operation with a battery is no longer possible.

Cabling plan Sunny Boy Smart Energy with Battery-Box Premium HVS/HVM and BCU 2.0
Pin at the RJ45 connector on the inverter | Signal | RJ45 connector on the battery |
|---|---|---|
1 | - | - |
2 | EN_GND | 8 |
3 | - | - |
4 | CAN_H | 4 |
5 | CAN_L | 5 |
6 | - | - |
7 | BAT_EN | 7 |
8 | - | - |