Procedure for the Initial Installation and Commissioning of the System


The procedure for installation, electrical connection, and commissioning of the system is described in the following. It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

Ensure that the requirements for the installation of the system components are fulfilled.

Manuals of the system components

Install rapid shutdown devices at the PV modules.

Manual for the rapid shutdown devices

Mount the inverter.

Manual of the inverter

Mount SMA Backup Start.

Manual for SMA Backup Start

Mount the backup solution SMA Backup Select or switch and socket for SMA Backup Secure.

Manual of SMA Backup Select or manual of switch and socket

Mount the energy meter.

Manual for the energy meter

Mount the battery.

Manual for the battery

Ensure that the requirements for the electrical connection are fulfilled.

Manuals of the system components

Connect the utility grid along with signal and power cables for backup operation.

Manual of the inverter

Connect the inverter to the backup solution.

Manual of the backup solution

Connect backup loads to the backup solution.

Manual of the backup solution

Connect the network cables to the router and other inverters to the inverter.

Manual of the inverter

Connect the energy meter to the inverter via Ethernet.

Manual of the inverter

Connect the data cables of the battery.

Manual of the inverter

Connect the rapid shutdown initiator.

Manual of the inverter

Connect to the multifunction relay (optional).

Manual of the inverter

Connect the PV modules to the inverter.

Manual of the inverter

Connect the battery power cables.

Manual of the inverter

Connect the additional grounding to the inverter.

Manual of the inverter

Commission the system.

Manual of the inverter

Make additional settings.

Manual of the inverter

Test backup operation.

Manual of the inverter